ICN › Carbon credit projects › Indonesia
210 MW Musi Hydro Power Plant, Bengkulu
Renewable energy carbon credit project in Bengkulu, Indonesia, registered with Verra (VCS) as VCS487.
The project activity is a new run-of-river type hydro power plant. Total installed capacity of the project is 210 MW, consisting of three (3) x 70 MW turbines. The project is owned and developed by PT. PLN (Persero), a state-owned electricity company. The project supplies electricity to the connected Sumatra grid…
Registry record
| Registry and ID | Verra (VCS) VCS487 |
|---|---|
| Project type | Renewable energy |
| Methodology | ACM0002 |
| Location | Bengkulu, Indonesia |
| Developer | PT. PLN (Persero) |
| Registry status | Registered |
| Vintage years | 2016–2026 |
| Credits issued | 7,635,581 tCO2e |
| Credits retired | 6,023,590 tCO2e |
| Credits not yet retired | 1,611,991 tCO2e |
Issuance figures are from the registry as of 2026-08-31.
View this project on the registry
About the methodology
ACM0002: Grid-connected electricity generation from renewable sources. Large wind, solar, hydro or geothermal plants that feed the grid. Credits are counted from the fossil power the plant's output is assumed to replace on that grid. Other projects using ACM0002
What to check for this type of project
Renewable energy credits pay for power from wind, solar, hydro or similar plants, counted against the fossil power the grid would otherwise use. They are avoidance credits: they prevent emissions rather than take carbon out of the air.
- Additionality: in many countries large wind and solar plants now pay for themselves, so ask whether carbon revenue was needed to build this one.
- In 2024 the ICVCM decided that the main grid renewable methodologies do not qualify for its Core Carbon Principles label. Check whether that matters for your claim.
- Older vintages from long-running plants are common and cheap. Many buyers prefer recent vintages.
Read more: The ICVCM CCP label · Carbon credits vs RECs · Avoidance vs removal credits · What a vintage means · Check an offer is genuine · How retirement works
Buy credits from this project
ICN sources credits for companies, checks them against the registry and retires them in the buyer's name with a public certificate.
Questions about 210 MW Musi Hydro Power Plant, Bengkulu
Is 210 MW Musi Hydro Power Plant, Bengkulu a registered carbon credit project?
Yes. It is on the Verra (VCS) registry as VCS487, with the registry status "Registered". You can check the public record on the registry yourself.
How many carbon credits has 210 MW Musi Hydro Power Plant, Bengkulu issued?
The registry shows 7,635,581 credits issued, 6,023,590 (79%) already retired by buyers and 1,611,991 not yet retired, as of 2026-08-31. Each credit is one tonne of CO2e.
Which methodology does 210 MW Musi Hydro Power Plant, Bengkulu use?
ACM0002 (Grid-connected electricity generation from renewable sources). Large wind, solar, hydro or geothermal plants that feed the grid. Credits are counted from the fossil power the plant's output is assumed to replace on that grid.
Which vintage years does 210 MW Musi Hydro Power Plant, Bengkulu cover?
The registry record covers vintages 2016–2026. Which vintages are still for sale changes over time, so ask for current stock before you buy.
Are credits from 210 MW Musi Hydro Power Plant, Bengkulu avoidance or removal credits?
ICN does not class this project as a removal, so treat its credits as emission reductions or avoidance. That is normal for most projects and fine for many claims, but net-zero standards ask for removals to balance residual emissions.
Can my company buy and retire credits from 210 MW Musi Hydro Power Plant, Bengkulu?
ICN can ask the seller for a quote. ICN retires the credits on the Verra (VCS) registry in your company's name and gives you a public certificate.
More projects in Indonesia
- Capacity Upgrade of Gunung Salak Geothermal Power Plant Project, Indonesia (VCS144, Renewable energy)
- Mobuya Mini Hydro Power Plant 3 x 1000 kW North Sulawesi, Indonesia (VCS238, Renewable energy)
- 50 MW Sipansihaporas Hydro Power Plant, North Sumatra (VCS486, Renewable energy)
- 82 MW Lau Renun Hydro Power Plant, North Sumatra (VCS488, Renewable energy)
- Wayang Windu Phase 2 Geothermal Power Project (VCS688, Renewable energy)
- Katingan Peatland Restoration and Conservation Project (VCS1477, Forestry & land use)